From: route@monster.com
Sent: Friday, April 08, 2016 12:07 PM
To: hg@apeironinc.com
Subject: Please review this candidate for: p6 PMP
This resume has been forwarded to
you at the request of Monster User xapeix03
|
|||||||
|
|||||||
|
|
|
||||||
|
||||||
|
Gregory Ewah Greg.ewah@gmail.com 773 934 3079 Profile:
A highly experienced Project Management Professional with experience
working in Construction and Oil and Gas industries. Offering over 8 years of
combined scholastic and professional experience in planning, estimates, field
works and office works. Skilled in dealing with managers, owners,
consultants, government officials and very good relationships with
co-employees as well as possessing strong leadership, team work and result
oriented personalities. Key
Skills: Primavera (P6), PRINCE 2, ITiL and MS Office. EDUCATION. University of Dundee
Dec. 2007 Centre for Energy, Petroleum and Mineral Law and
Policy
Master
of Business Administration in Oil and Gas Management University
of Benin
Dec. 2003 Faculty
of Social
Sciences
Bachelor
of Science in Business
Administration
GPA 3.9/ 4.0
PROFESSIONAL CERTIFICATIONS. v Certified Primavera P6 Professional
Fundamentals Rel. 8.3 v PRINCE2 Project Management
Practitioner (PMP) Certified v Information Technology
Infrastructure Library (ITIL v3) v Requirement Engineering
(Certification Leading to ISEB International Diploma in Business Analysis.)
Certified v Certified Nebosh International
General Certificate in Occupational Health and Safety CAREER SUMMARY. ExxonMobil
November 2010 to
Present Project
Planner. · Analyze schedules for potential impacts and advise
project manager of potential problems, work interference on schedule
difficulties and assist in the resolution · Travel to Europe, United Arab Emirate and Africa to
conduct vessels inspection and interface on offshore project issues · Working with the project team, sequence project
activities to ensure that project progress is on schedule · Provide required information, reports, documentation
and schedules for Change Order creation and submission · Create and maintain baseline for project schedules · Incorporates updates in the project schedule based
on input from the organization · Review all portfolio contractual documentation in
regards to project planning and project controls · Anticipate potential problems and proactively
resolves them using independent judgment and innovation in finding solutions · Facilitates communication between key support
functions within the department · Break activities down into smaller weighted steps
and track the completion of the steps to determine the activity percent
complete · Input the planning issues into the project’s
critical issues risk log. Review planning risks and ensure the risk register
is updated accordingly.
Bankers
Ware
House
July 2009 to October 2010 Project
Scheduler ·
Created cost loaded
plans with complete logical dependencies, baselines for
monitoring/evaluation, complete WBS coding structure, critical paths and
physical progress measures ·
Developed recovery
programs to ensure project critical milestones are met on time ·
Created a monthly
milestone report to ensure that the Project Manager is aware of which
projects are at risk and allow adequate time to make changes to the critical
path to bring implementation date back on schedule ·
Managed the contractor
plans to ensure that accurate physical progress was recorded ·
Ensured effective
change control takes place on any live or near live project ·
Generated weekly
progress reports including milestone slippage charts and pictograms showing
project progress and highlighting milestones at risk at a glance Royal Bank of Scotland
(RBS).
July 2008 to March 2009. Project
Scheduler.
·
Prepared and
maintained project control schedules ·
Ensured that the
project schedules accurately reflect the scope of the project and are of
sufficient detail to enable project progress to be accurately monitored,
reported and communicated ·
Prepared project
progress reports for review and validation by the project manager ·
Identified variances
from the project baseline plan and propose corrective actions to minimise /
mitigate delays ·
Monitored progress
against tasks carried out by project team ·
Ensured plans are
fully resourced and cost loaded, monitored progress and made changes as
required ·
Reported actual
performance and variance against plan and forecasted outcomes ·
Monitored and audited
contractor plans ensuring they comply with company requirements ·
Risk Analysis and
developing contingency plans to prepare for changed objectives Grontmij
(Formerly Carl
Bro)
July 2007 to June 2008. Project Planner on Scottish
Water’s Capital Investment Program. A
program of improvement works on behalf of Scottish Water Projects
cover the Scottish Water region, across Edinburgh, Dundee, Perth and Glasgow
which included: · Widespread improvements to sewage works to upgrade
the quality of water released into rivers and the sea · Refurbishing water supply works to improve the
quality of tap water · Projects to control odor from treatment works · Schemes to provide mains drainage to areas without
public sewers Responsibilities · Prepared a project work breakdown structure (WBS)
and plan in accordance with the requirements · Assigned activities, created relationship between
activities, baseline, scheduled and optimized project plan · Assisted in the preparation and monitoring of
Project budgets · Monitored the works to ensure that quality
requirements are met, identifying any changes to the scope of the contract
works · Ensured project plan is fully resourced and cost
loaded and monitored progress to the plan and made changes as required · Updated activities and schedule on a weekly basis · Identified all critical paths within a project by
using float path analysis · Reported actual performance and variance against
plan and forecast outcomes · Highlighted key milestone and critical path issues
to members of the team, provided an assessment of the impact of such issues
and recommended solutions to correct the position · Improved collaboration by quickly emailing entire
projects to project managers · Assisted in Coordinating labor, material, equipment
and subcontractors to ensure on-schedule, on-budget completion Nigeria
Liquefied Natural Gas
(NLNG)
June 2005 to October 2005. Project
Planner.
· Discussed and agreed resources/timescales with the
project manager · Ensured all activities within the scope of the work
are included in programs · Issued programs in accordance with document control
systems · Gathered information for progress reporting · Updated Plan through the lifetime of the project · Maintained cause and effect records in liaison with
the project manager · Assisted in regular resource planning and updating · Assisted in progress reporting against program · Pursued subcontractors programs & ensured
alignment with those of the company · Worked under pressure to tight deadlines References
will be supplied on request. |
|
|
|||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||
|
|